Three-Phase Mobilisation Approach

Client: Yondr, 1 Petersfield Ave, Slough
Service: Critical + Commercial
Client since: 2025
Contract status: Expanded Contract
Total area: 41,300 m2
Buildings supported: 3Operatives: 20

Challenge

An unresponsive vendor without data-centre expertise had left a demotivated workforce and underperforming waste-management subcontractors. C4 had six weeks to mobilise and train staff, complete emergency tasks, and rebuild trust while the campus expanded.

What C4 did

Phase 1: Transferred and trained the existing workforce, managed urgent ad hoc requests, and inducted the supply chain.

Phase 2: Recruited and equipped staff for the second data centre at 50% capacity while continuing subcontractor integration.

Phase 3: Completed recruitment when the second site reached 100% capacity.

Results

  • Improved cleaning quality by 14%.
  • Increased staff retention by 70%.
  • Completed a three-phase mobilisation supporting three buildings.

“C4 supported us through a demanding mobilisation and campus expansion. Their team responded to urgent requirements, supported the existing workforce and developed the service as the second building came into operation.”

Alan Grayly

Services
we offer

Server Room Cleaning

Comms Room Cleaning

Clinical Cleans

Specialised Deep Clean

Post Construction Cleans to IS0-14644/1

IT Equipment Cleaning

Air Particle Testing

On-going Intermediate Cleans

Migration Project Clean

Class 7-8 clean